X888,做题了,项目管理的成本计算。请指点计算方法。谢谢

我弟弟要参加考试了,问我一个往年的考题,答案是C。但是不知道如何计算的。我也不知道。请指教如何计算。给个计算方法的链接也行。谢谢了。

A project manager estimates a project will take 14 weeks at a cost of $60,000.In signing the contract documents, the customer imposes a penalty for late completion of $2,000 per estimates that the maximum possible crashing of the project duration is 4 weeks, at an additional cost of $9,000.Assuming that the project manager is going to make the decision and that cost is the driving criteria for the project manager’s organization, what is the expected project cost?
A.$69,000
B.$71,000
C.$70,000
D.$62,000

某项目经理估算一项目要花14 周时间成本$60,000 在签合同文件时客户要求延期完工赔偿$2,000 项目工期的最大可能的赶工时间是4 周附加成本$9,000 假定成本是主要的衡量标准项目经理要作出决策什么是预期的项目成本
A.$69,000
B.$71,000
C.$70,000
D.$62,000
Report

Replies, comments and Discussions:

  • 工作学习 / 学科技术讨论 / X888,做题了,项目管理的成本计算。请指点计算方法。谢谢
    我弟弟要参加考试了,问我一个往年的考题,答案是C。但是不知道如何计算的。我也不知道。请指教如何计算。给个计算方法的链接也行。谢谢了。

    A project manager estimates a project will take 14 weeks at a cost of $60,000.In signing the contract documents, the customer imposes a penalty for late completion of $2,000 per estimates that the maximum possible crashing of the project duration is 4 weeks, at an additional cost of $9,000.Assuming that the project manager is going to make the decision and that cost is the driving criteria for the project manager’s organization, what is the expected project cost?
    A.$69,000
    B.$71,000
    C.$70,000
    D.$62,000

    某项目经理估算一项目要花14 周时间成本$60,000 在签合同文件时客户要求延期完工赔偿$2,000 项目工期的最大可能的赶工时间是4 周附加成本$9,000 假定成本是主要的衡量标准项目经理要作出决策什么是预期的项目成本
    A.$69,000
    B.$71,000
    C.$70,000
    D.$62,000
    • If project is completed on time, cost is 60k+9k=69k; if project delays, cost is 69k+2k=71k. Expected cost is (69k+71k)/2=70k.